CRESS
Adakah RED dibenarkan menandatangani perjanjian FCAS (Frequency Control Ancillary Services) dengan pengendali grid bagi sistem BESS yang layak dibangunkan dalam ladang solar, serta bagi projek berdiri sendiri (standalone)?
Tiada keperluan untuk menandatangani perjanjian perkhidmatan sampingan (ancillary services) bagi pembangunan BESS. Walau bagaimanapun, terdapat set keperluan teknikal, kawalan dan pemantauan yang perlu dipatuhi oleh BESS bagi sistem hibrid dan berdiri sendiri (standalone).
CRESS
How is wheeling availability is determined?
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
How is wheeling availability is determined?
Under clause 8.14(a), the BESS is “dispatchable by GSO as per system requirements”. Under what circumstances will GSO be dispatching power from the BESS— i. Is this for emergency / occasional use only under unusual circumstances, and otherwise, the RED w