CRESS
Adakah terdapat sebarang had kepada interkoneksi (kapasiti eksport) selain daripada PSS? Contohnya, adakah kapasiti interkoneksi ditetapkan pada 50% daripada kapasiti AC loji?
Jawapan: Kapasiti eksport hendaklah mengikut cadangan kapasiti yang dijalankan oleh PSS. Iaitu, kapasiti AC.
CRESS
How is wheeling availability is determined?
How is wheeling availability is determined?
Under clause 8.14(a), the BESS is “dispatchable by GSO as per system requirements”. Under what circumstances will GSO be dispatching power from the BESS— i. Is this for emergency / occasional use only under unusual circumstances, and otherwise, the RED w