Soalan Lazim
Program Peralihan Tenaga
CRESS
Bagi seksyen 8.14 (a) Garis Panduan CRESS, bolehkah kami memahami bahawa bagi loji 100MWac, kapasiti boleh guna selain daripada kapasiti nominal bagi BESS hendaklah sekurang-kurangnya 50MW/200MWh?
Bagi kes 50MW/200MWh di atas, adakah kami perlu memenuhi syarat ini setiap hari sepanjang tempoh PPA, iaitu setiap hari loji perlu mempunyai keupayaan untuk menyalurkan tenaga 200MWh terus ke sistem grid daripada BESS, walaupun pada hari cuaca buruk apabi
CRESS Acceleration Package
Who pays the SAC under the Acceleration Package?
What fixed SAC rate is offered for RED under the CRESS Acceleration Package?
Will the fixed SAC rate for RED be reviewed during the 10-year period?
Why is the SAC for RED fixed for 10 years?
What SAC rate will be paid by the GC under the CRESS Acceleration Package?
What cost components are considered in the SAC framework for both RED and GC?
Why should the GC bear part of the CRESS-related cost?
Will a GC be charged twice for network access?