Sekiranya kami mengisytiharkan kapasiti firm bagi hari berikutnya, berapa lamakah loji perlu mengekalkan kapasiti firm tersebut (contohnya 6 jam, 12 jam dan sebagainya)?
Sila rujuk jawapan yang diberikan dalam Soalan 14 di atas.
CRESS
How is wheeling availability is determined?
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
How is wheeling availability is determined?
Under clause 8.14(a), the BESS is “dispatchable by GSO as per system requirements”. Under what circumstances will GSO be dispatching power from the BESS— i. Is this for emergency / occasional use only under unusual circumstances, and otherwise, the RED w