Green Consumer and Renewable Energy Developer (RED) Policies

Based on the following situation, is the customer allowed to participate in CRESS for Factory 1 since it will be energised in the future?

Screenshot-2026-03-05-154739.png

i. The off-taker has two factories, Factory 1 and the newly constructed Factory 2.

ii. Factory 1 is supplied by the existing 132kV substation.

iii. Factory 1 initial Maximum Demand is 60 MW in which the off-taker has submitted a request for a staggered additional load (final MD as 130 MW), which will cater for Factory 2 as well: Year 2026 – 95 MW; Year 2027 – 130 MW; Year 2028 – 130 MW.

iv. The ESA for Factory 2 has been signed, however the Maximum Demand is still being negotiated and is subject to change.

v. Supply to Factory 2 has been energized this year with the new substation.

vi. Supply to Factory 1 from the new substation will be energized January next year and the existing substation will cease operations.

Even though Factory 1 will take from new 132kV substation in the future, Factory 1 is considered as an existing consumer since already take supply from existing 132kV substation prior to 30 September 2024. 

Based on an announcement made by the YAB Minister in January 2025, CRESS is now open to all consumers including existing demand. Therefore, Factory 1's eligibility to participate in CRESS is subject to amendment of the CRESS guidelines."

With reference to section 6.5, we understand that a RED is allowed to contract with more than 1 Green Consumer, but can a RED have more than 1 project site for 1 Green Consumer? Example 1: Green Consumer with a demand of 150 MW under 2 site locations (100 MW and 50 MW). With reference to section 6.15, EUC may also offer billing services to RED and Green Consumer for energy supplied by RED to Green Consumer, what do these "billing services" entail and what are the charges for it? Based on our understanding of sections 8.1 and 8.19, qualified Green Consumers (GC) should be existing customers, connected to the high and/or medium voltage lines, who have or will receive electricity on or after September 30, 2024. Would the regulator consider expanding the start date of qualified GCs in order to have a greater pool of demand for RED to provide supply to and to justify investments at scale? With respect to the classification of a new Green Consumer, we are enquiring on behalf of a potential data centre off-taker, with an ESA for a 450 MVA connection with TNB. The data centre site has already energised at a very minimal power usage for testing and commissioning in preparation for their client in Q1 and Q2 next year. Can they still be considered as a new Green Consumer under CRESS? What rules govern the maximum demand the offtaker states in their CRESA and will this be in MW (vs MWh)? Will this be the same as CGPP where the offtaker’s ability to contract is capped by their max demand in MW?