CRESS
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
- BESS will be connected directly to the grid and will be independent from the backfeed agreement. GSO will determine the charging and discharging of BESS.
- There is no restriction in the backfeed agreement.
- Backfeed Agreement is a standard agreement meant for backfeed supply, where there will be no maximum demand charge. An Electricity Supply Agreement (ESA) is a special agreement for normal supply for high voltage, public distribution, and cogeneration customers.
CRESS
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr