Frequently Asked Questions
Energy Transition Program
Corporate Green Power Programme
What is the max MW/ MWh that can be contracted by corporate?
Company B is a sister company of Company A. Would both company be qualified for submission?
Can the Solar Power Producer also be the Corporate Consumer?
Can cogen operator with public license participate in VPPA scheme? What is the difference between the company install solar power generation for producing electricity for own consumption compared with VPPA.
Understand that preference shares are allowed via non-convertible preference shares with debt characteristics and no voting rights are allowed. In such case, is the preference shares holder considered as one of the consortium members?
i) Company A submits an application of 30MW through consortium A (company A + Company B). Company A holds 50% shareholding.
ii) Company A submits another application of 30MW through consortium B (company A + company C) . Company A holds 50% shareholding.
Is this arrangement allowed? Or Company A submission through consortium A is already counted as 1 full submission?
CRESS
Managing Nodal Points Between LSS5 and CRESS
Can multi-technology be allowed to firm up output?
If the ESA has already been signed with a scheduled start date, how will delays in the GEP be managed if there is no corresponding delay from the Green Consumer (GC)? Would TNB be open to provide temporary supply to GC in case the GEP is delayed?
i. If TNB agrees to provide a temporary supply to the GC due to delays from the RED, what would be the terms and conditions for such temporary supply arrangements?
ii. In the event of a delay from the RED, would there be any financial penalties, compensation, or adjustments to the ESA to account for the discrepancy in readiness? If so, how are these calculated and communicated to the GC?
iii. Is there a maximum allowable delay period for the RED before the ESA needs to be renegotiated or canceled?
What is the Backfeed Charge Rate?