Can additional demand from CGPP customer which have yet to be in operation participate in CRESS?
Yes, new demand and additions to existing consumers are allowed.
CRESS
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other