CREAM
Could we clarify on the agency/entity responsible for conducting the PSS are LEGA, TNB, or approved consultants?
The Power System Study (PSS) will be conducted directly by the EUC. LEGA is required to engage with the EUC for initiating the study. Please refer to Appendix 2 of the Guideline on the application process flow.
CREAM
What is the type of licenses required (e.g. generation license, supply license)?
What are the circumstances under which energy is considered "free to grid"?
Are there procedure for selling excess via NEDA, detailed registration and notification requirements?
Please help to provide guidance on approved REC registries, platforms, or any local tracking systems recognized by ST.
Is there any guideline for license application?