Dalam seksyen 11, dinyatakan bahawa "SAC hendaklah dikaji semula pada setiap Tempoh Kawal Selia". Apakah definisi "Tempoh Kawal Selia," dan adakah terdapat andaian mengenai sejauh mana turun naik SAC akan berubah (jika ada).
Sila rujuk definisi di bawah garis panduan
CRESS
What is the dispatch priority during solar energy generation? E.g. is it to fully charge the BESS first and export to grid once BESS is fully charged or vice versa? Or is the battery mainly to help firm up/smooth out the half-hourly firm output?
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
Under clause 8.14(a), the BESS is “dispatchable by GSO as per system requirements”. Under what circumstances will GSO be dispatching power from the BESS— i. Is this for emergency / occasional use only under unusual circumstances, and otherwise, the RED w
Under clause 8.14(a), the BESS is “dispatchable by GSO as per system requirements”. Under what circumstances will GSO be dispatching power from the BESS— i. Is this for emergency / occasional use only under unusual circumstances, and otherwise, the RED w
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?