Application Process and Documentation
With reference to section 13.1, we understand that Single Buyer will start accepting applications from 30 September 2024 onwards, however, to clarify is there a timeline to submit (as were the case in CGPP)?
With reference to Section 13.1, while the Single Buyer will begin accepting applications from 30 September 2024, there is currently no specified timeline or deadline for submissions at this time.
Application Process and Documentation
For Section 13.4 (h), can the Land Lease Agreement be substituted with a MoU/Term Sheet for the purpose of application submission and only proceed to execute the definitive contract upon successful application, as it was the case with CGPP.
With reference to section 13.4(i), can we clarify if this refers to the full-fledged, definitive contract between the RED and the Green Consumer? Or can a MoU/Term Sheet suffice for application purposes, to be followed by the definitive contract upon succ
With reference to section 13.4(i), can we clarify if this refers to the full-fledged, definitive contract between the RED and the Green Consumer? Or can a MoU/Term Sheet suffice for application purposes, to be followed by the definitive contract upon succ
With reference to section 13.4(j), can we clarify what are the default declaration documents to be furnished? Further to this, will ST release appendices/forms similar to those required under the CGPP?
For Section 13.4 (h), can the Land Lease Agreement be substituted with a MoU/Term Sheet for the purpose of application submission and only proceed to execute the definitive contract upon successful application, as it was the case with CGPP.