Eligibility Criteria of CC
Is there any ways for large franchise MNCS with multiple branches and outlets eligible to participate in CGPP? As the franchise outlets tariff are categorized under Tariff B where Maximum Demand is unavailable. However, this sector has huge interest to offset carbon emission via REC.
Yes, large franchise MNCs with tariff B accounts may apply to join CGPP. For existing Tariff B customers, the actual MD can be obtained from the bottom side at the bill. For new Tariff B customers or existing Tariff B where the information is
not available in bill due to legacy information, the Tariff B customers may declare MD up to 60kW per TNB account. The 60kW MD is inline with MD declaration for whole current meters in Schedule 1 of Connection Charges Book for Low Voltage customers.
Eligibility Criteria of CC
Under the eligibility criteria, can the consumer is the higher education intitutions? As the RM10m paid up company is not comply under higher education institutions body.
C In terms of maximum demand, can we submit the anticipated demand for the next 21 years, which will significantly increase over the 21-year?
C In terms of maximum demand, can we submit the anticipated demand for the next 21 years, which will significantly increase over the 21-year?
Are data centers considered a service company?
Under the eligibility criteria, can the consumer is the higher education intitutions? As the RM10m paid up company is not comply under higher education institutions body.