CRESS
The customer has signed the ESA, and the supply is given before the CRESS effective date. The customer declared the staggered Maximum Demand as follows. Can customers join CRESS for the additional staggered load for the coming years? Eg, Customer final MD is 100MW with staggered load declaration. Year 1 = 10 MW (current year) Year 5 = 50 MW Year 15 = 100MW (final load).
Customer may only join CRESS for request of additional load above 100MW only which is the final load of existing supply contract
CRESS
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other