Application and Qualifications
Customers have signed ESA and supply is given before effective date of CRESS. Can customers close their account and submit new supply application to join CRESS under the new account?
Customers may close or terminate their accounts at any time. However, customers are subject to related charges, such as Liquidated Damages, Refundable Connection Charge, or any other charges as provided under the supply contract terms and conditions.
Since CRESS is open for new customers and existing customers with additional load only, the customers who close their accounts are not allowed to join CRESS if the same customers open a new account at the same premises.
Application and Qualifications
What is the definition of new customer?
What is the definition of new customer?
Customer has signed the ESA, and the supply is given before the CRESS effective date. Customer declared the staggered Maximum Demand as below. Can customer join CRESS for the additional staggered load for the coming years?
Eg, Customer final MD is 100MW with staggered load declaration.
Year 1 = 10 MW (current year)
Year 5 = 50 MW
Year 15 = 100MW (final load).
Customer has signed the ESA, and the supply is given before the CRESS effective date. Customer declared the staggered Maximum Demand as below. Can customer join CRESS for the additional staggered load for the coming years?
Eg, Customer final MD is 100MW with staggered load declaration.
Year 1 = 10 MW (current year)
Year 5 = 50 MW
Year 15 = 100MW (final load).
When can a CRESS application be submitted?