CRESS · Dispatch, Curtailment and Day-Ahead Scheduling
Is there any guarantee that energy to be exported?
Can Single Buyer dispatch the energy from the Solar System in normal circumstances?
How is wheeling availability is determined?
Under Clause 8.13 of the Guidelines, “GEP shall declare a Firm Output for the day-ahead scheduling in the Market Participant Interface (MPI)”. Are there any penalties if the day-ahead output declared does not match the actual output? What is the margin for error?
Under Clause 8.13 of the Guidelines, "GEP shall declare a Firm Output for the day-ahead scheduling in the Market Participant Interface (MPI)”.
i. What is the allowed imbalance/ tolerance for the day-ahead scheduling?
ii. At what resolution/interval should the energy output be provided?