Dispatch, Curtailment and Day-Ahead Scheduling

Under Clause 8.13 of the Guidelines, "GEP shall declare a Firm Output for the day-ahead scheduling in the Market Participant Interface (MPI)”. i. What is the allowed imbalance/ tolerance for the day-ahead scheduling? ii. At what resolution/interval should the energy output be provided?

i. We do not specify the imbalance/tolerance allowed for day-ahead scheduling.

ii. Every half an hour interval.