Preliminary check/study/PSS
If PSS rejected by TNB at NEDA stage, does it meant the CGPP application will be fully rejected?
The NEDA application is consider unsuccessful. Referring to Clause 2.1 of Guidelines for NEDA, PSS is part of pre-requisites for NEDA registration.
Preliminary check/study/PSS
Please advice if 132kV substation that is not in the list is allowed if preliminary check with PSS consultant shows that injection is feasible.
Please advice if 132kV substation that is not in the list is allowed if preliminary check with PSS consultant shows that injection is feasible.
Is Full PSS is required for NEDA? or PSS stage 1?
Is Full PSS is required for NEDA? or PSS stage 1?