Grid Connection and Technical Requirements
Will the GSO require the BESS to be capable of providing grid forming and/or black start capability as part of this section 8.16 requirement? What other functions/capabilities shall the GSO be testing the BESS for in connection to this section?
The inverter types chosen by RED for either BESS or solar shall follow the requirements of the Grid Code for Peninsular Malaysia and as advised by EUC at the point of requesting a grid connection (via PSS). The inverters may be required to provide grid-forming and/or black-start functions. For detailed information on BESS Compliance tests, please refer to Appendix D of RE SAA. The agreement will be provided by EUC upon CRESS application.
Grid Connection and Technical Requirements
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
With reference to section 8.10, in the event of a withdrawal of Green Consumer, can the RED reapply to participate in CRESS if they found a new Green Consumer to replace the one who had withdrawn? Will that new Green Consumer need to be a new electricity user?
What is the AC/DC ratio acceptable for the scheme?
What is the AC/DC ratio acceptable for the scheme?
What is the AC/DC ratio acceptable for the scheme?