Based on our understanding of sections 8.1 and 8.19, qualified Green Consumers (GC) should be existing customers, connected to the high and/or medium voltage lines, who have or will receive electricity on or after September 30, 2024. Would the regulator c
The Energy Commission is currently focused on maintaining the existing start date for qualified GCs, as the Government has approved this requirement to align with the broader market framework and strategic objectives.
CRESS
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
RED’s Declared Monthly Energy Output = 1,000 MWh RED’s Actual Monthly Energy Output = 1,000 MWh GC’s Consumption = 1,200 MWh Balance consumption from TNB = 200 MWh Given the GC’s TNB Tariff is C2, which has a Peak tariff of RM 0.365/kWh and an off-peak t
Will there be MD be chargeable to Green Consumer?