Based on our understanding of sections 8.1 and 8.19, qualified Green Consumers (GC) should be existing customers, connected to the high and/or medium voltage lines, who have or will receive electricity on or after September 30, 2024. Would the regulator c
The Energy Commission is currently focused on maintaining the existing start date for qualified GCs, as the Government has approved this requirement to align with the broader market framework and strategic objectives.
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?