With reference to section 6.15, EUC may also offer billing services to RED and Green Consumer for energy supplied by RED to Green Consumer, what do these "billing services" entail and what are the charges for it?
EUC (TNB) will provide monthly billing and collection services on behalf of REDs to their GCs for green energy consumption and SAC. The charges are subject to negotiation.
Green Consumer and Renewable Energy Developer (RED) Policies
What rules govern the maximum demand the offtaker states in their CRESA and will this be in MW (vs MWh)? Will this be the same as CGPP where the offtaker’s ability to contract is capped by their max demand in MW?
With respect to the classification of a new Green Consumer, we are enquiring on behalf of a potential data centre off-taker, with an ESA for a 450 MVA connection with TNB. The data centre site has already energised at a very minimal power usage for testing and commissioning in preparation for their client in Q1 and Q2 next year. Can they still be considered as a new Green Consumer under CRESS?
What rules govern the maximum demand the offtaker states in their CRESA and will this be in MW (vs MWh)? Will this be the same as CGPP where the offtaker’s ability to contract is capped by their max demand in MW?
With respect to the classification of a new Green Consumer, we are enquiring on behalf of a potential data centre off-taker, with an ESA for a 450 MVA connection with TNB. The data centre site has already energised at a very minimal power usage for testing and commissioning in preparation for their client in Q1 and Q2 next year. Can they still be considered as a new Green Consumer under CRESS?
Based on the following situation, is the customer allowed to participate in CRESS for Factory 1 since it will be energised in the future?