With reference to section 6.5, we understand that a RED is allowed to contract with more than 1 Green Consumer, but can a RED have more than 1 project site for 1 Green Consumer? Example 1: Green Consumer with a demand of 150 MW under 2 site locations (100
Under the Guidelines, a Green Consumer is allowed to source green electricity from more than one RED up to its maximum energy as declared in the CRESA with the EUC.
CRESS
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
RED’s Declared Monthly Energy Output = 1,000 MWh RED’s Actual Monthly Energy Output = 1,000 MWh GC’s Consumption = 1,200 MWh Balance consumption from TNB = 200 MWh Given the GC’s TNB Tariff is C2, which has a Peak tariff of RM 0.365/kWh and an off-peak t
Will there be MD be chargeable to Green Consumer?