For Section 13.4 (h), can the Land Lease Agreement be substituted with a MoU/Term Sheet for the purpose of application submission and only proceed to execute the definitive contract upon successful application, as it was the case with CGPP.
With reference to Section 13.4(h), applicants are required to secure a definitive contract/agreement at the application stage. This requirement is in place to affirm a committed partnership and support the reliable delivery of the project. While we understand this may necessitate additional time and resources, the definitive agreement is essential to meet the standards outlined in the guidelines.
CRESS
Section 6.11 of the CRESS Guidelines outlines that "The EUC shall carry out the billing process and issue the relevant bill to the Green Consumer based on meter readings at both RED (MRED) and Green Consumer (MGC) premises. The meter reading at RED and Gr
Referring to Clause 7.6 of the September CRESS Guidelines, which outlines that "The RED shall also enter into Backfeed Agreement with the EUC to obtain electricity supply for the plant's own consumption, backfeed requirement during construction, and other
Referring to Clause 6.14(b) of the September CRESS Guidelines outlines "EUC will issue an electricity bill to the Green Consumer for every billing cycle period, being: (a) the period beginning on the Commencement Date and ending on the date on which the f
RED’s Declared Monthly Energy Output = 1,000 MWh RED’s Actual Monthly Energy Output = 1,000 MWh GC’s Consumption = 1,200 MWh Balance consumption from TNB = 200 MWh Given the GC’s TNB Tariff is C2, which has a Peak tariff of RM 0.365/kWh and an off-peak t
Will there be MD be chargeable to Green Consumer?