Grid Connection and Technical Requirements
What is the AC/DC ratio acceptable for the scheme?
RED to determine the appropriate AC/DC ratio based on expected technical compliance stipulated in Grid Code and other GSO technical documents - as long as the required firming of 50% of GEP capacity for 4 hrs is fulfilled.
*For the avoidance of doubt, the verification of this requirement is done at the commissioning stage, before commercial operation commences.
Grid Connection and Technical Requirements
Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
With reference to section 8.10, in the event of a withdrawal of Green Consumer, can the RED reapply to participate in CRESS if they found a new Green Consumer to replace the one who had withdrawn? Will that new Green Consumer need to be a new electricity user?
What is the AC/DC ratio acceptable for the scheme?